Ken installed lighting fixtures last week. This is one of the wall sconces in the living room area.
Great progress made today... The septic system which has been installed for over a year finally went "live" today. Now we actually have a working toilet. We can start moving the toilets out of the garage and into the bathrooms. We would even have running water if the sinks were installed. Hmm... another day!
All the rooms are just about finished with the hardwood flooring. Bob and Isidro are working on hanging doors and the stairway. All the downstairs tiling is finished. We have lots of extra tile-- thinking of going into the coaster making business.
All the rooms are just about finished with the hardwood flooring. Bob and Isidro are working on hanging doors and the stairway. All the downstairs tiling is finished. We have lots of extra tile-- thinking of going into the coaster making business.